AACE Estimate Classes

AACE estimate classes rank capital cost estimates from Class 5 (concept screening) through Class 4 (feasibility) to Class 1 (check estimate), each with a typical accuracy range.

EconomicsLast reviewed by Soukayna Jermouni

In plain terms

Every cost estimate is a range, and its width depends on how much of the project has been defined. AACE International's Recommended Practice 18R-97 sorts process-industry estimates into five classes. Class 5 is the least defined; Class 1 the most.

The ranges are not fixed percentages. They are typical bounds, and the actual range of any estimate depends on technology maturity, site complexity and estimating effort.

Typical range

ClassProject definitionTypical useLow rangeHigh range
50–2 %Concept screening−20 % to −50 %+30 % to +100 %
41–15 %Feasibility study−15 % to −30 %+20 % to +50 %
310–40 %Budget authorisation−10 % to −20 %+10 % to +30 %
230–75 %Control or bid−5 % to −15 %+5 % to +20 %
165–100 %Check estimate−3 % to −10 %+3 % to +15 %

A first-of-a-kind green hydrogen plant tends toward the wider end of each range, because electrolyzer and balance-of-plant costs are still moving.

Why it moves LCOH

An LCOH inherits the uncertainty of its CAPEX estimate. In a Class 4 feasibility study, the CAPEX share of LCOH carries a range that may run up to +50 %, so two sites that differ by less than the resulting LCOH range are not clearly ranked yet. Investment decisions typically require at least a Class 3 estimate.

Common mistake

Typical range

−50 % / +100 % (Class 5) to −3 % / +3 % (Class 1, best case) accuracy range around the point estimate[1]

Sources

  1. Recommended Practice 18R-97: Cost Estimate Classification System, as Applied in Engineering, Procurement, and Construction for the Process Industries, AACE International, 2020