Stack Degradation
Stack degradation is the gradual loss of electrolyzer cell performance over operating time, usually given as an electrolyzer degradation rate in %/1,000 h or µV/h of cell voltage rise.
In plain terms
As an electrolyzer runs, catalysts lose activity, membranes thin and contact resistances grow. To keep the same hydrogen output, each cell needs a little more voltage every month. That rise is stack degradation.
It is reported two ways. µV/h or mV/kh is the cell voltage increase per operating hour (1 mV/kh = 1 µV/h). %/1,000 h is the same rise as a share of the starting voltage. The US DOE declares a stack at end of life when voltage has risen 10 %, and derives stack lifetime from the degradation rate.
Typical range
| Technology | Clean Hydrogen JU (2020 SoA) | US DOE (2022 status) | DOE stack lifetime |
|---|---|---|---|
| Alkaline | 0.12 %/1,000 h | 3.2 mV/kh (0.17 %) | 60,000 h |
| PEM | 0.19 %/1,000 h | 4.8 mV/kh (0.25 %) | 40,000 h |
| Solid oxide | 1.9 %/1,000 h | 6.4 mV/kh (0.50 %) | 20,000 h |
Solid oxide rates are measured on different test bases by the two agencies. Variable operation, frequent starts and impurities in the feed water can push real-world rates above these values.
Why it moves LCOH
Degradation hits LCOH twice. First, rising voltage means rising specific energy consumption, so the plant buys more electricity per kilogram each year. Second, the stack must be replaced at end of life, a large mid-project CAPEX line. A PEM stack with a 40,000 h life running 5,000 h a year needs replacing about every eight years.
Common mistake
Related terms
Sources
- Strategic Research and Innovation Agenda 2021–2027: key performance indicators (AEL, PEMEL, SOEL tables), Clean Hydrogen Joint Undertaking, 2022
- Technical Targets for Liquid Alkaline Electrolyzer Stacks and Systems, U.S. Department of Energy, Hydrogen and Fuel Cell Technologies Office, 2022
- Technical Targets for Proton Exchange Membrane Electrolysis, U.S. Department of Energy, Hydrogen and Fuel Cell Technologies Office, 2022
- Technical Targets for High-Temperature Electrolysis, U.S. Department of Energy, Hydrogen and Fuel Cell Technologies Office, 2022