Renewable Fuels of Non-Biological Origin (RFNBO)
Renewable fuels of non-biological origin (RFNBO) are the EU category for fuels, such as green hydrogen, whose energy comes from renewables other than biomass; only RFNBOs count toward EU targets.
In plain terms
RFNBO is how EU law says "green hydrogen". The Renewable Energy Directive, (EU) 2018/2001, Art. 2(36), defines RFNBOs as liquid and gaseous fuels whose energy content comes from renewable sources other than biomass. Hydrogen from electrolysis qualifies only if its electricity meets the 2023/1184 rules; derivatives such as ammonia and e-methanol can qualify on the same basis.
Two delegated regulations, both adopted on 10 February 2023, set the detailed rules. Keep them apart:
| Regulation | What it covers |
|---|---|
| (EU) 2023/1184 | When electricity counts as renewable: direct connection, grid routes, additionality, temporal and geographic correlation |
| (EU) 2023/1185 | How to calculate greenhouse gas savings for RFNBOs |
Regulation (EU) 2024/1408 later aligned a technical term in 2023/1184 with the amended Directive; the thresholds did not change.
Typical range
To count, an RFNBO must achieve at least 70 % greenhouse gas savings against the fossil reference, calculated with the 2023/1185 method; Commission guidance C/2025/2983 confirms the threshold. Under RED Art. 22a, Member States must ensure at least 42 % of hydrogen used in industry is RFNBO by 2030, and 60 % by 2035.
Why it moves LCOH
RFNBO rules constrain plant design. They decide which electricity counts, when, and from where. Meeting them can mean oversized renewables, storage or lost production hours, which all raise LCOH. Hydrogen that fails them cannot count toward EU targets, which limits its value to EU buyers.
Common mistake
Related terms
Sources
- Directive (EU) 2018/2001 on the promotion of the use of energy from renewable sources (consolidated text), Art. 2(36) and Art. 22a, EUR-Lex, Official Journal of the European Union, 2023
- Commission Delegated Regulation (EU) 2023/1184 (consolidated text incl. 2024/1408), EUR-Lex, Official Journal of the European Union, 2024
- Commission Delegated Regulation (EU) 2023/1185, EUR-Lex, Official Journal of the European Union, 2023
- Commission guidance C/2025/2983 on renewable fuels of non-biological origin targets, EUR-Lex, Official Journal of the European Union, 2025