On 13 November 2026, Oman's Hydrom awarded two green hydrogen projects in Duqm with a combined planned output of about 121,000 tonnes of hydrogen a year by 2032 (Hydrom via PR Newswire) [1]. One plans 1.45 GW of solar and 1 GW of electrolysis. The fiscal terms even name the next engineering stage: they offer "potential further relief during the Front-End Engineering Design (FEED) phase".
That detail matters. Winning land or a subsidy is not a project. Between the award and a final investment decision (FID) sit two engineering gates: pre-FEED and FEED. Each must answer different questions, at a different level of cost certainty.
This article sets out what green hydrogen pre-FEED vs FEED must deliver, how accurate each estimate should be, and where projects most often skip ahead too early.
The stage sequence: concept, pre-FEED, FEED, FID
Most industrial owners run a stage-gated process. Names vary (FEL 1, 2, 3; Select and Define), but the logic is the same: spend a little to kill bad options early, then spend more only on the option that survives.
Recent hydrogen projects show the sequence in practice:
- Pre-FEED to FEED: the BarMar subsea hydrogen pipeline between Barcelona and Marseille entered FEED in July 2026. Its pre-FEED had "confirmed the project's overall technical feasibility, established the design basis for the offshore pipeline and compression station, and identified a preferred corridor route" (Pipeline & Gas Journal) [2].
- Pre-FEED for a large ammonia plant: in August 2026, ORNX selected KBR for the pre-FEED of a project in Morocco designed for about 560,000 tonnes a year of ammonia and about 900 MW of electrolyzers, with the stated aim to "accelerate towards the FEED and Final Investment Decision" (KBR) [3].
- FEED with an EPC option: in April 2026, Norwegian Hydrogen awarded Worley Rosenberg the FEED for the 25 MW RjukanLH2 liquid hydrogen project, with an exclusive option for EPC and an EPC execution plan developed in parallel (Worley) [4].
- FEED to a fabrication contract: thyssenkrupp nucera's FEED for an approximately 600 MW project in Europe aims at an engineering, procurement and fabrication contract in the next phase, with FID "thereafter" (thyssenkrupp nucera) [5].
Before any of this comes the concept or screening study. Its job is to rank sites and configurations, not to design anything. Our guide to green hydrogen site selection criteria covers that first filter.
What pre-FEED must deliver
Pre-FEED is a selection study. It compares a few credible configurations and picks one. A good pre-FEED for a green hydrogen or derivative plant answers these questions:
- Power supply: off-grid, grid-connected or hybrid? What solar and wind mix, and is a battery needed? See off-grid vs grid-connected green hydrogen and battery storage for green hydrogen.
- Electrolyzer technology and size: alkaline or PEM, and the ratio of electrolyzer to renewable capacity. See our AWE vs PEM comparison and capacity factor optimization.
- Water source and treatment route: desalination, municipal supply or reuse, and the cooling choice. See green hydrogen water consumption per kg.
- Buffer storage and compression: how much hydrogen storage is needed to feed a steady downstream process.
- Regulatory fit: if the product targets the EU, whether the configuration can meet RFNBO rules. See RFNBO additionality rules explained.
- A first design basis: the document FEED will build on.
The output is a preferred option, a design basis, and a cost estimate good enough to decide whether FEED is worth paying for.
What FEED must deliver
FEED is a definition study. It freezes the selected option and turns it into documents that contractors can price and lenders can test. BarMar's FEED scope is typical: "finalize the pipeline route, complete the compression station design, prepare permitting documentation and develop technical specifications for construction and material procurement" (Pipeline & Gas Journal) [2].
For a hydrogen production plant, FEED typically adds:
- Process flow diagrams, P&IDs and heat and material balances for the selected train
- Plot plan, equipment list and datasheets for long-lead items (electrolyzers, transformers and rectifiers, compressors, storage)
- Electrical single-line diagrams and the grid or renewable interface
- Hazard studies and the permitting package
- An execution plan and a contracting strategy (EPC, EPCM or split packages)
- A cost estimate firm enough to support FID and financing
FEED is also where the electrolyzer supplier's scope gets pinned down. Quotes that cover the stack only can hide a large share of the installed cost, a gap we covered in Chinese electrolyzer cost vs Western.
How accurate each estimate should be
The clearest way to compare the two stages is by cost-estimate class. ASTM E2516, based on AACE International's recommended practices, links the share of the project that is defined to the expected accuracy. Alberta Infrastructure publishes the ranges for building and general construction (Alberta Infrastructure) [6]:
| Class | Project definition | End use | Expected accuracy (low / high) |
|---|---|---|---|
| 5 | 0–2% | Feasibility or screening | -20% to -30% / +30% to +50% |
| 4 | 1–15% | Concept study | -10% to -20% / +20% to +30% |
| 3 | 10–40% | Budget control | -5% to -15% / +10% to +20% |
| 2 | 30–70% | Control or bid / tender | -5% to -10% / +5% to +15% |
A common industry convention maps the concept study to Class 5, pre-FEED to Class 4 and FEED to Class 3. Process-plant ranges under AACE's own practice for that industry can be wider than the construction ranges above. The same source warns that the range "should always be determined through risk analysis of the specific project and should never be pre-determined".
A pre-FEED number can still be 20–30% too low. Building an offtake price or an auction bid on it carries that risk.
Our article on electrolyzer CAPEX vs discount rate shows how far a CAPEX error moves LCOH.
Why projects skip ahead, and what it costs
Skipping stages is not new. Independent Project Analysis (IPA) reported that "only 40% of projects completely finish Front End Loading II decision gate before moving forward" (Offshore) [7]. That figure comes from oil and gas, and dates from 2011.
New energy faces stronger pressure. IPA, writing in JPT, notes that "most industrial projects are committed at the end of scope development and before front-end engineering and design (FEED)", and that new energy businesses often commit earlier, naming hydrogen supply projects among them (JPT) [8].
Subsidy schemes add clocks. Winners of the EU's 2024 Hydrogen Bank auction must reach financial close within 2.5 years of signing the grant agreement and start production within 5 years, and must post a completion guarantee (European Commission) [9]. In the second auction, projects totaling 1.9 GW of electrolyzer capacity withdrew, most of the 2.3 GW awarded (S&P Global) [10]. A bid priced on a Class 5 or Class 4 number is exposed. See European Hydrogen Bank auction results and why green hydrogen projects get cancelled.
Reaching FID: engineering is necessary, not sufficient
A finished FEED does not guarantee FID. The 30 MW Barrow Green Hydrogen project in Cumbria, UK, reached FID in May 2026 with a long-term PPA, an offtaker and UK government support through Hydrogen Allocation Round 1 in place (Plug Power) [11]. Engineering, power, offtake and money had to close together. Our guide to hydrogen offtake agreement structure covers the commercial side.
A simple rule follows: run the commercial work in step with the engineering. Pre-FEED should test the offtake price. FEED should give lenders a cost they can underwrite.
Checklist: are you ready to leave pre-FEED?
- One configuration selected, with the rejected options and reasons documented
- Hourly renewable profile and electrolyzer sizing agreed, with capacity factor stated
- Water source and treatment route confirmed with a supply study
- Storage and compression sized to the downstream demand profile
- RFNBO or other certification pathway checked, if relevant
- Design basis issued and signed off by the owner
- Estimate class and accuracy range stated on every cost number shared with offtakers or lenders
Conclusion
Pre-FEED chooses. FEED defines. Treating a pre-FEED number as a FEED number is how projects get to an auction or an offtake deal with a cost they cannot hold.
Hyzen helps teams do the selection work faster. The platform already models renewable input, electrolyzer sizing, water, gas conditioning, compression, storage and RFNBO checks, and Hyzen is building its LCOH and balance-of-plant engines next. Start with the free Site Screener to test a location before you commission pre-FEED.
Editorial Notes
- The mapping of concept, pre-FEED and FEED to AACE Classes 5, 4 and 3 is a widely used convention, not a fixed rule; owners and contractors define their own gates.
- The accuracy table uses ranges published for building and general construction. Process-industry ranges can be wider.
- The IPA 40% figure is from 2011 and from oil and gas projects; it is cited as context, not as a hydrogen-specific statistic.
References
[1] Hydrom. Oman awards two green hydrogen projects in Duqm and launches Round 4 green-powered data centre hydrogen auction at COP31. PR Newswire (2026).
[2] Pipeline & Gas Journal. H2med's BarMar hydrogen pipeline enters FEED phase. Pipeline & Gas Journal (2026).
[3] KBR. KBR selected by ORNX for low-cost ammonia pre-FEED study supporting landmark Morocco project. GlobeNewswire (2026).
[4] Worley. Worley Rosenberg awarded FEED contract for RjukanLH2 hydrogen project. Worley (2026).
[5] thyssenkrupp nucera. thyssenkrupp nucera signs FEED study for a 600 MW green hydrogen project in Europe. thyssenkrupp nucera (2025).
[6] Alberta Infrastructure. Classes of Construction Cost Estimates, Design & Technology Series #19. Government of Alberta (2025).
[7] Roobaert, N. Project success hinges on FEED completion. Offshore (2011).
[8] Wertz, P. Mitigating risks of early commitment in new energy projects. Journal of Petroleum Technology (2023).
[9] European Commission. IF24 Auction. European Commission (2026).
[10] S&P Global Commodity Insights. Most project capacity of second EU Hydrogen Bank auction withdraws. S&P Global (2025).
[11] Plug Power. Plug and Carlton Power: Barrow Green Hydrogen achieves FID, bringing industrial-scale hydrogen to the UK. Plug Power (2026).